A farm carries out three operations: land preparation (3 days with 2 workers), planting (2 days with 3 workers) and weeding. The weeding task requires a total of 96 man‑hours. The farm wants all work completed within 7 calendar days. Weeding can start only after land preparation is finished (i.e., on day 4) and may run concurrently with planting. Each worker works 8 hours per day and is paid ₦500 per day. Determine the minimum number of workers needed for weeding and the total labour cost for the whole schedule.

Answer Options

A. 4 workers; total labour cost = ₦16,000
B. 5 workers; total labour cost = ₦20,000
Correct Answer C. 3 workers; total labour cost = ₦12,000
D. 2 workers; total labour cost = ₦8,000
Correct Answer
C
Correct Option:
3 workers; total labour cost = ₦12,000

About This Question

This is Waec Model Questions Vol1 2019 Agricultural Science Question 49. It is one of the objective questions from the 2019 Waec Model Questions Vol1 Agricultural Science examination.

Difficulty level: Medium .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support