A local government has four development projects with the following data: Project A costs ₦90 million and requires 50 staff, benefit score 130; Project B costs ₦70 million, requires 40 staff, benefit 100; Project C costs ₦60 million, requires 30 staff, benefit 80; Project D costs ₦50 million, requires 20 staff, benefit 70. The total budget available is ₦200 million and the total staff that can be employed is at most 100. Which combination of projects yields the maximum total benefit without exceeding either the budget or staff limit? State the maximum total benefit.

Answer Options

Correct Answer A. 280
B. 250
C. 260
D. 270
Correct Answer
A
Correct Option:
280

About This Question

This is Neco Model Questions Vol1 2018 Government Question 16. It is one of the objective questions from the 2018 Neco Model Questions Vol1 Government examination.

Difficulty level: Hard .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support