A public procurement project is valued at \(₦200\) million. Historical data shows that in 12\% of similar projects a corrupt official siphons off 8\% of the contract value, while in 5\% of projects the siphoned amount is 15\% due to collusion with multiple officials. The remaining projects have no loss. Assuming these events are mutually exclusive, calculate the expected monetary loss due to corruption for a new project of the same value. Give your answer in millions of naira to two decimal places.