A freight company can use either rail or road to move goods. Fixed cost per trip: rail £500, road £200. Variable cost per ton‑km: rail £0.04, road £0.06. Maximum load per trip: rail 30 t, road 10 t. The company must transport 45 t over 350 km. Determine the minimum total cost and the combination of trips (how many rail and road trips, and the load on each) that achieves this minimum cost.