A local council proposes building a community centre that costs \(£2{,}000{,}000\) to construct. It is expected to generate an annual benefit of \(£300{,}000\) and incur annual operating costs of \(£50{,}000\). The centre has a useful life of 10 years and the council uses a discount rate of 5 %. Calculate the net present value (NPV) of the project and state whether the council should approve it.