Gce Model Questions Vol1 2020 Geography Question 50

Practice objective / multiple choice question 50 from the 2020 Gce Model Questions Vol1 Geography examination.

Gce Model Questions Vol1 2020 Geography Objective / Multiple Choice Hard Difficulty
Question 50 GCE_MODEL_QUESTIONS_VOL1 • 2020 • GEOGRAPHY • objective

A 120 km railway line is proposed to link two cities. Construction cost is £480 million (paid at year 0). Annual operating cost is £12 million. Passenger trips start at 2 million per year and grow at 3 % per year; the average fare is £15 and rises with inflation at 2 % per year. The railway saves £4 million per year in road‑maintenance costs and reduces CO₂ emissions valued at £0.8 per tonne; emission reductions start at 5 000 t yr⁻¹ and grow at 1 % per year. Using a real discount rate of 5 % and a 30‑year analysis period, calculate the net present value (NPV) of the project. Is the project economically viable (NPV > 0)?

Answer Options

Correct Answer A. £261 million (positive, project viable)
B. £210 million (positive, project viable)
C. £320 million (positive, project viable)
D. £-45 million (negative, project not viable)
Correct Answer
A
Correct Option:
£261 million (positive, project viable)

About This Question

This is Gce Model Questions Vol1 2020 Geography Question 50. It is one of the objective questions from the 2020 Gce Model Questions Vol1 Geography examination.

Difficulty level: Hard .