A local council has £2\,million to allocate among three projects. Project X costs £1.2\,million and yields an annual benefit of £300\,000 for 5 years. Project Y costs £0.8\,million and yields £250\,000 per year for 4 years. Project Z costs £0.9\,million and yields £200\,000 per year for 6 years. Using a discount rate of 5\% per annum, determine which combination of projects maximises the total present value of benefits without exceeding the budget. List the projects that should be funded.