A government plans to build a 100 km highway. Construction cost of \(\text{₦}2.5\) billion is incurred at the start. Annual maintenance cost will be \(\text{₦}120\) million for 20 years. The highway is expected to generate an annual economic benefit of \(\text{₦}300\) million in the first year, growing at 3 % per year. Using a discount rate of 8 % per annum, calculate the net present value (NPV) of the project (in billions of Naira, rounded to two decimal places) and state whether the project should be undertaken.