Neco Model Questions Vol1 2019 Economics Question 50

Practice objective / multiple choice question 50 from the 2019 Neco Model Questions Vol1 Economics examination.

Neco Model Questions Vol1 2019 Economics Objective / Multiple Choice Hard Difficulty
Question 50 NECO_MODEL_QUESTIONS_VOL1 • 2019 • ECONOMICS • objective

A road project requires an initial construction outlay of \(\text{₦}500\) million at time 0. It will generate annual benefits of reduced travel cost equal to \(\text{₦}120\) million in year 1, growing at 3 % per year thereafter. Annual maintenance costs start at \(\text{₦}20\) million in year 1 and also grow at 3 % per year. Using a discount rate of 8 % per year and assuming an infinite horizon, calculate the net present value (NPV) of the project (in million naira). Should the project be undertaken?

Answer Options

A. 1300
B. 1700
Correct Answer C. 1500
D. 900
Correct Answer
C
Correct Option:
1500

About This Question

This is Neco Model Questions Vol1 2019 Economics Question 50. It is one of the objective questions from the 2019 Neco Model Questions Vol1 Economics examination.

Difficulty level: Hard .