Neco 2025 Computer Studies Question 42

Practice objective / multiple choice question 42 from the 2025 Neco Computer Studies examination.

Neco 2025 Computer Studies Objective / Multiple Choice Medium Difficulty
Question 42 NECO • 2025 • COMPUTER_STUDIES • objective

A software development team follows the Waterfall model with five phases. The planned durations are: Requirements \(3\) weeks, Design \(4\) weeks, Implementation \(6\) weeks, Testing \(5\) weeks, Maintenance \(8\) weeks. Testing can start only after half of the Implementation phase is completed, and Maintenance begins immediately after Testing ends. What is the minimum total time (in weeks) to complete the project?

Answer Options

A. 26
Correct Answer B. 23
C. 21
D. 24
Correct Answer
B
Correct Option:
23

About This Question

This is Neco 2025 Computer Studies Question 42. It is one of the objective questions from the 2025 Neco Computer Studies examination.

Difficulty level: Medium .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support