A software development team follows the Waterfall model with five phases. The planned durations are: Requirements \(3\) weeks, Design \(4\) weeks, Implementation \(6\) weeks, Testing \(5\) weeks, Maintenance \(8\) weeks. Testing can start only after half of the Implementation phase is completed, and Maintenance begins immediately after Testing ends. What is the minimum total time (in weeks) to complete the project?