Neco 2025 Computer Studies Question 31
Practice objective / multiple choice question 31 from the 2025 Neco Computer Studies examination.
A software project is scheduled for \(800\) hours using the Waterfall model with the following planned phase allocations: Requirements 10%, Design 15%, Coding 40%, Testing 20%, Maintenance 15%. During the coding phase, the team conducts testing simultaneously for \(30\%\) of the coding time, so those hours count toward both coding and testing. How many hours of the project schedule are saved because of this simultaneous testing?
Answer Options
About This Question
This is Neco 2025 Computer Studies Question 31. It is one of the objective questions from the 2025 Neco Computer Studies examination.