A proposed road segment of 50 km will cost \(\text{₦}120\) billion to construct. Expected annual traffic is 12 000 vehicles, each paying a toll of \(\text{₦}2{,}500\). Operating cost per vehicle is \(\text{₦}500\) and fixed annual maintenance is \(\text{₦}1.5\) billion. Using a discount rate of 8 % and a 20‑year analysis period, calculate the net present value (NPV) of the road project. An alternative railway would cost \(\text{₦}150\) billion, carry 8 000 passengers per year at a fare of \(\text{₦}5{,}000\) each, with operating cost \(\text{₦}1{,}200\) per passenger and fixed maintenance \(\text{₦}2\) billion per year. Compute the railway's NPV under the same assumptions and state which option is financially preferable.

Answer Options

A. Road NPV ≈ -₦140.2 billion; Railway NPV ≈ -₦160.5 billion; road is relatively better but both are unviable
B. Road NPV ≈ -₦120.0 billion; Railway NPV ≈ -₦150.0 billion; road is relatively better but both are unviable
Correct Answer C. Road NPV ≈ -₦134.5 billion; Railway NPV ≈ -₦169.3 billion; road is relatively better but both are unviable
D. Road NPV ≈ -₦130.0 billion; Railway NPV ≈ -₦180.0 billion; road is relatively better but both are unviable
Correct Answer
C
Correct Option:
Road NPV ≈ -₦134.5 billion; Railway NPV ≈ -₦169.3 billion; road is relatively better but both are unviable

About This Question

This is Neco 2023 Geography Question 10. It is one of the objective questions from the 2023 Neco Geography examination.

Difficulty level: Hard .