Neco 2022 Data Processing Question 24

Practice objective / multiple choice question 24 from the 2022 Neco Data Processing examination.

Neco 2022 Data Processing Objective / Multiple Choice Medium Difficulty
Question 24 NECO • 2022 • DATA_PROCESSING • objective

The five steps of the data processing cycle take the following times for a particular transaction: input = 2 s, processing = 5 s, storage = 3 s, output = 2 s, control = 1 s. The control step runs concurrently with the processing step, overlapping exactly 1 second of processing time. What is the total time required to complete the cycle for this transaction?

Answer Options

A. 11 s
B. 13 s
C. 10 s
Correct Answer D. 12 s
Correct Answer
D
Correct Option:
12 s

About This Question

This is Neco 2022 Data Processing Question 24. It is one of the objective questions from the 2022 Neco Data Processing examination.

Difficulty level: Medium .