A software project follows the Waterfall model with five phases whose original time allocations are: Requirements 20%, Design 25%, Implementation 30%, Testing 15% and Maintenance 10% of the total project time. The total planned time is 1200 hours. Due to a design change, the Implementation phase actually requires 20% more time than its original allocation, and the Testing phase is reduced proportionally so that the overall project time remains 1200 hours. What is the new duration (in hours) of the Testing phase?

Answer Options

A. 96
B. 180
Correct Answer C. 108
D. 120
Correct Answer
C
Correct Option:
108

About This Question

This is Neco 2019 Computer Studies Question 11. It is one of the objective questions from the 2019 Neco Computer Studies examination.

Difficulty level: Medium .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support