Neco 2018 Data Processing Question 29

Practice objective / multiple choice question 29 from the 2018 Neco Data Processing examination.

Neco 2018 Data Processing Objective / Multiple Choice Medium Difficulty
Question 29 NECO • 2018 • DATA_PROCESSING • objective

In a data processing system the average times recorded per transaction are: Input \(2\) ms, Processing \(8\) ms, Output \(3\) ms, Storage \(5\) ms, and Control \(10\) ms (the Control stage runs only once per batch, not per transaction). If a batch of \(250\) transactions is processed sequentially, what is the total time to complete the batch in seconds?

Answer Options

A. 7.00 seconds
Correct Answer B. 4.51 seconds
C. 4.5 seconds
D. 45.1 seconds
Correct Answer
B
Correct Option:
4.51 seconds

About This Question

This is Neco 2018 Data Processing Question 29. It is one of the objective questions from the 2018 Neco Data Processing examination.

Difficulty level: Medium .