Three development projects are proposed for a local government. Project X costs \(120\) million naira and will generate a uniform benefit of \(30\) million naira per year for 6 years; the discount rate applicable is 10 %. Project Y costs \(150\) million naira and will generate a uniform benefit of \(40\) million naira per year for 5 years; the discount rate is 12 %. Project Z costs \(100\) million naira and will generate a uniform benefit of \(20\) million naira per year for 8 years; the discount rate is 8 %. Only one project can be funded. Using the net present value (NPV) method, determine which project should be selected.

Answer Options

A. Project Z should be selected (NPV ≈ 13.20 million naira, highest).
B. Project X should be selected (NPV ≈ 12.30 million naira, highest).
Correct Answer C. Project Z should be selected (NPV ≈ 14.95 million naira, highest).
D. Project Y should be selected (NPV ≈ 13.80 million naira, highest).
Correct Answer
C
Correct Option:
Project Z should be selected (NPV ≈ 14.95 million naira, highest).

About This Question

This is Neco 2017 Government Question 27. It is one of the objective questions from the 2017 Neco Government examination.

Difficulty level: Hard .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support