An information system processes data in cycles consisting of three stages: Input (4 min), Process (6 min) and Output (3 min). After each output, the system checks the error level; if the error exceeds 2 % a feedback stage of 5 min is performed before the next input. The probability that the error exceeds the threshold for any given cycle is 0.25, independent of other cycles. If the system processes 8 independent batches, what is the expected total time (in minutes) required to complete all cycles?

Answer Options

A. 108 minutes
B. 112 minutes
Correct Answer C. 114 minutes
D. 120 minutes
Correct Answer
C
Correct Option:
114 minutes

About This Question

This is Neco 2017 Data Processing Question 17. It is one of the objective questions from the 2017 Neco Data Processing examination.

Difficulty level: Medium .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support