A software project has the following estimated phase durations (in months): Requirements 4, Design 6, Coding 12, Testing 3, Maintenance 2. In the Waterfall model phases are sequential. In an Incremental model a new phase can start when 50% of the preceding phase is complete. Assuming phases overlap as described, calculate the total project duration for each model and state which model finishes earlier.

Answer Options

A. Incremental model - 15 months (12 months shorter than Waterfall)
B. Waterfall model - 27 months (10 months longer than Incremental)
C. Incremental model - 20 months (7 months shorter than Waterfall)
Correct Answer D. Incremental model - 17 months (10 months shorter than Waterfall)
Correct Answer
D
Correct Option:
Incremental model - 17 months (10 months shorter than Waterfall)

About This Question

This is Gce Model Questions Vol1 2021 Computer Studies Question 46. It is one of the objective questions from the 2021 Gce Model Questions Vol1 Computer Studies examination.

Difficulty level: Medium .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support