A software project has the following estimated phase durations (in months): Requirements 4, Design 6, Coding 12, Testing 3, Maintenance 2. In the Waterfall model phases are sequential. In an Incremental model a new phase can start when 50% of the preceding phase is complete. Assuming phases overlap as described, calculate the total project duration for each model and state which model finishes earlier.