A government infrastructure project requires an initial outlay of £200 million today. It is expected to generate real benefits of £80 million at the end of year 1, £90 million at the end of year 2 and £100 million at the end of year 3. The nominal discount rate is 8 % per annum and the expected inflation rate is 3 % per annum. Using the real discount rate, calculate the net present value (NPV) of the project and state whether it should be undertaken.