Gce Model Questions Vol1 2019 Computer Studies Question 6

Practice objective / multiple choice question 6 from the 2019 Gce Model Questions Vol1 Computer Studies examination.

Gce Model Questions Vol1 2019 Computer Studies Objective / Multiple Choice Medium Difficulty
Question 6 GCE_MODEL_QUESTIONS_VOL1 • 2019 • COMPUTER_STUDIES • objective

A software project is estimated to require (800) person‑hours in total, divided among four phases as follows: Phase 1 - 20 % of the total, Phase 2 - 30 %, Phase 3 - 30 %, Phase 4 - 20 %. During execution the following adjustments occur: Phase 1 actually takes 15 % more time than estimated, Phase 2 takes 5 % less, Phase 3 takes 10 % less because of code reuse, and Phase 4 is completed exactly as estimated. What is the actual total number of person‑hours spent on the project?

Answer Options

A. 800
B. 812
C. 824
Correct Answer D. 788
Correct Answer
D
Correct Option:
788

About This Question

This is Gce Model Questions Vol1 2019 Computer Studies Question 6. It is one of the objective questions from the 2019 Gce Model Questions Vol1 Computer Studies examination.

Difficulty level: Medium .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support