A software project is estimated to require (800) person‑hours in total, divided among four phases as follows: Phase 1 - 20 % of the total, Phase 2 - 30 %, Phase 3 - 30 %, Phase 4 - 20 %. During execution the following adjustments occur: Phase 1 actually takes 15 % more time than estimated, Phase 2 takes 5 % less, Phase 3 takes 10 % less because of code reuse, and Phase 4 is completed exactly as estimated. What is the actual total number of person‑hours spent on the project?