City Guilds Model Questions Vol1 2025 Engineering Question 33

Practice objective / multiple choice question 33 from the 2025 City Guilds Model Questions Vol1 Engineering examination.

City Guilds Model Questions Vol1 2025 Engineering Objective / Multiple Choice Medium Difficulty
Question 33 CITY_GUILDS_MODEL_QUESTIONS_VOL1 • 2025 • ENGINEERING • objective

In a risk assessment for a workshop, the following annual probabilities of occurrence are given: electrical fault - 0.04 yr⁻¹, chemical spill - 0.12 yr⁻¹. The severity ratings (on a 1-5 scale) are 4 for the electrical fault and 5 for the chemical spill. Probability ratings are assigned as follows: \(00.20\) → 5. The overall risk score is the sum of the individual risk scores (probability rating \(\times\) severity rating). If the acceptable risk threshold is 20, decide whether additional control measures are required and state the total risk score.

Answer Options

A. Total risk score = 18; additional control measures are required.
Correct Answer B. Total risk score = 28; additional control measures are required.
C. Total risk score = 24; additional control measures are required.
D. Total risk score = 28; no additional control measures are required.
Correct Answer
B
Correct Option:
Total risk score = 28; additional control measures are required.

About This Question

This is City Guilds Model Questions Vol1 2025 Engineering Question 33. It is one of the objective questions from the 2025 City Guilds Model Questions Vol1 Engineering examination.

Difficulty level: Medium .