City Guilds Model Questions Vol1 2024 Engineering Question 34

Practice objective / multiple choice question 34 from the 2024 City Guilds Model Questions Vol1 Engineering examination.

City Guilds Model Questions Vol1 2024 Engineering Objective / Multiple Choice Medium Difficulty
Question 34 CITY_GUILDS_MODEL_QUESTIONS_VOL1 • 2024 • ENGINEERING • objective

A workshop risk assessment lists three hazards with the following probability (P) and severity (S) scores (on a 1-5 scale): Hazard A - P = 4, S = 3; Hazard B - P = 2, S = 5; Hazard C - P = 3, S = 2. The overall risk rating for each hazard is calculated as \(R = P \times S\). After implementing control measures, the probabilities change to: Hazard A - P = 2; Hazard B - P = 1; Hazard C - P = 2 (severity scores remain unchanged). Compute (a) the total risk rating before the controls, (b) the total risk rating after the controls, and (c) the percentage reduction in total risk.

Answer Options

Correct Answer A. Initial total risk 28, after controls 15, reduction ≈46.4%
B. Initial total risk 26, after controls 13, reduction ≈50.0%
C. Initial total risk 30, after controls 14, reduction ≈53.3%
D. Initial total risk 28, after controls 16, reduction ≈42.9%
Correct Answer
A
Correct Option:
Initial total risk 28, after controls 15, reduction ≈46.4%

About This Question

This is City Guilds Model Questions Vol1 2024 Engineering Question 34. It is one of the objective questions from the 2024 City Guilds Model Questions Vol1 Engineering examination.

Difficulty level: Medium .