In a round‑robin CPU scheduler the time quantum is 20 ms and each context switch adds an overhead of 2 ms. A process requires a total of 70 ms of CPU time.\nHow many quanta will the process need, and what is the total elapsed time (including all context‑switch overheads) for the process to complete?

Answer Options

A. 4 quanta; total time 80 ms
Correct Answer B. 4 quanta; total time 78 ms
C. 3 quanta; total time 66 ms
D. 5 quanta; total time 102 ms
Correct Answer
B
Correct Option:
4 quanta; total time 78 ms

About This Question

This is City Guilds Model Questions Vol1 2023 Information Technology Question 49. It is one of the objective questions from the 2023 City Guilds Model Questions Vol1 Information Technology examination.

Difficulty level: Easy .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support