City Guilds Model Questions Vol1 2023 Engineering Question 3

Practice objective / multiple choice question 3 from the 2023 City Guilds Model Questions Vol1 Engineering examination.

City Guilds Model Questions Vol1 2023 Engineering Objective / Multiple Choice Hard Difficulty
Question 3 CITY_GUILDS_MODEL_QUESTIONS_VOL1 • 2023 • ENGINEERING • objective

A metal part requires a cylindrical hole of diameter \(20\) mm and depth \(50\) mm. Two machining options are considered:\n\n1. Drilling with a twist drill: cutting speed \(30\) m·min\(^{-1}\), feed \(0.15\) mm·rev\(^{-1}\), tool life \(45\) min.\n2. Boring with a single‑point tool: cutting speed \(20\) m·min\(^{-1}\), feed \(0.10\) mm·rev\(^{-1}\), tool life \(60\) min.\n\nThe machine spindle speed cannot exceed \(1500\) rev·min\(^{-1}\). Each tool change takes \(2\) min. For a production run of \(100\) holes, determine which process gives the lower total machining time (including tool changes) and the corresponding total cost if the drilling cost is \(\text{₦}150\) per minute and the boring cost is \(\text{₦}200\) per minute.

Answer Options

A. Drilling; total time 80 min, total cost ₦12000
B. Boring; total time 70 min, total cost ₦14000
Correct Answer C. Drilling; total time 72 min, total cost ₦10800
D. Boring; total time 84 min, total cost ₦16800
Correct Answer
C
Correct Option:
Drilling; total time 72 min, total cost ₦10800

About This Question

This is City Guilds Model Questions Vol1 2023 Engineering Question 3. It is one of the objective questions from the 2023 City Guilds Model Questions Vol1 Engineering examination.

Difficulty level: Hard .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support