In a workshop risk‑assessment three hazards A, B and C are identified. Their consequence scores are 4, 3 and 5 respectively (higher means more severe). The probability scores (on a 1-5 scale) satisfy \(p_{B}=p_{A}+1\) and \(p_{C}=p_{A}-2\). The overall risk rating, defined as \(\sum (\text{consequence}\times\text{probability})\), is 29. Determine the probability scores for A, B and C and state which hazard requires the highest control priority (use the highest individual risk product; if tied, choose the hazard with the larger consequence).
Answer Options
About This Question
This is City Guilds Model Questions Vol1 2023 Engineering Question 2. It is one of the objective questions from the 2023 City Guilds Model Questions Vol1 Engineering examination.
Difficulty level: Medium .
Master the Exam!
You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.