City Guilds Model Questions Vol1 2021 Engineering Question 29
Practice objective / multiple choice question 29 from the 2021 City Guilds Model Questions Vol1 Engineering examination.
A component can be produced either by casting or by machining. Casting requires a one‑time mould cost of \(\text{₦}5{,}000\) and a per‑unit cost of \(\text{₦}150\); a single casting batch can contain up to 20 units and needs 4 days of lead time. Machining has no tooling cost, a per‑unit cost of \(\text{₦}250\), and each unit takes 0.5 day to machine. An order for 45 units must be completed within 12 days. Determine the production mix (how many units by casting and how many by machining) that meets the deadline at minimum total cost, and state that minimum cost.
Answer Options
About This Question
This is City Guilds Model Questions Vol1 2021 Engineering Question 29. It is one of the objective questions from the 2021 City Guilds Model Questions Vol1 Engineering examination.
Difficulty level: Hard .
Master the Exam!
You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.