During a 1000‑hour production run three machines require preventive maintenance:\n\n- Machine A: one maintenance of 8 h after every 200 h of operation.\n- Machine B: two maintenances of 5 h each after every 250 h of operation.\n- Machine C: one maintenance of 6 h after every 300 h of operation.\n\nAt most two machines can be under maintenance at the same time, and any overlapping period reduces the effective downtime by 20 % of the overlapped duration (i.e., an overlapped hour counts as 0.8 h of downtime). Determine the minimal total effective downtime (in hours) for the plant over the 1000‑hour period.

Answer Options

A. 20
B. 26
Correct Answer C. 22
D. 24
Correct Answer
C
Correct Option:
22

About This Question

This is City Guilds Model Questions Vol1 2021 Engineering Question 18. It is one of the objective questions from the 2021 City Guilds Model Questions Vol1 Engineering examination.

Difficulty level: Hard .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support