City Guilds Model Questions Vol1 2020 Information Technology Objective / Multiple Choice Easy Difficulty
Question 13 CITY_GUILDS_MODEL_QUESTIONS_VOL1 • 2020 • INFORMATION_TECHNOLOGY • objective

Three processes A, B and C are scheduled in the order A → B → C on a single‑CPU system. Their CPU bursts and I/O wait times are as follows:\n\n- Process A: CPU 20 ms, I/O wait 10 ms, then CPU 15 ms.\n- Process B: CPU 30 ms, I/O wait 5 ms, then CPU 20 ms.\n- Process C: CPU 25 ms, no I/O.\n\nAssume that while a process is performing I/O, the CPU can execute another ready process. Determine (i) the total elapsed time from the start of A to the completion of C, and (ii) the CPU utilisation percentage over this interval.

Answer Options

A. Total time 115 ms; CPU utilisation 95 %
Correct Answer B. Total time 110 ms; CPU utilisation 100 %
C. Total time 110 ms; CPU utilisation 95 %
D. Total time 105 ms; CPU utilisation 100 %
Correct Answer
B
Correct Option:
Total time 110 ms; CPU utilisation 100 %

About This Question

This is City Guilds Model Questions Vol1 2020 Information Technology Question 13. It is one of the objective questions from the 2020 City Guilds Model Questions Vol1 Information Technology examination.

Difficulty level: Easy .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support