An engineering workshop must produce \(300\) identical components in an 8‑hour shift (\(480\) min). Two manufacturing processes are available:\n\n- Process A: setup time \(20\) min, processing time \(1\) min per component, unit cost \(\text{₦}0.60\), maximum capacity \(250\) components per shift.\n- Process B: setup time \(15\) min, processing time \(2\) min per component, unit cost \(\text{₦}0.40\), maximum capacity \(200\) components per shift.\n\nBoth setups are incurred only if the corresponding process is used. Determine how many components should be produced by each process so that the total production cost is minimized while meeting the \(300\)-component requirement and not exceeding the shift time.

Answer Options

Correct Answer A. Process A: 155 components, Process B: 145 components
B. Process A: 160 components, Process B: 140 components
C. Process A: 140 components, Process B: 160 components
D. Process A: 150 components, Process B: 150 components
Correct Answer
A
Correct Option:
Process A: 155 components, Process B: 145 components

About This Question

This is City Guilds Model Questions Vol1 2019 Engineering Question 36. It is one of the objective questions from the 2019 City Guilds Model Questions Vol1 Engineering examination.

Difficulty level: Hard .

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support