City Guilds Model Questions Vol1 2018 Engineering Question 28

Practice objective / multiple choice question 28 from the 2018 City Guilds Model Questions Vol1 Engineering examination.

City Guilds Model Questions Vol1 2018 Engineering Objective / Multiple Choice Hard Difficulty
Question 28 CITY_GUILDS_MODEL_QUESTIONS_VOL1 • 2018 • ENGINEERING • objective

An equipment consists of two components, A and B, connected in series. Component A has a mean time between failures (MTBF) of \(200\) hours and a repair time of \(4\) hours. Component B has an MTBF of \(300\) hours and a repair time of \(6\) hours. Assuming failures follow independent exponential distributions, calculate the expected total downtime of the equipment over \(1000\) operating hours.

Answer Options

A. 35
B. 45
C. 30
Correct Answer D. 40
Correct Answer
D
Correct Option:
40

About This Question

This is City Guilds Model Questions Vol1 2018 Engineering Question 28. It is one of the objective questions from the 2018 City Guilds Model Questions Vol1 Engineering examination.

Difficulty level: Hard .