A company uses a just-in-time inventory system. If the company's supplier is unable to deliver goods on time, what is the likely impact on the company's production schedule?

Answer Options

Correct Answer A. The production schedule will be delayed
B. The production schedule will be accelerated
C. The production schedule will remain unchanged
D. The production schedule will be cancelled
Correct Answer
A
Correct Option:
The production schedule will be delayed

About This Question

This is Post Utme Uniport 2020 Commerce Question 28. It is one of the objective questions from the 2020 Post Utme Uniport Commerce examination.