Post Utme Unilorin 2018 Economics Question 25
Practice objective / multiple choice question 25 from the 2018 Post Utme Unilorin Economics examination.
A firm is considering two investment projects. Project A has a higher expected return but also a higher risk. Project B has a lower expected return but also a lower risk. What is the opportunity \cost of choo\sing Project A over Project B?