A company is considering the installation of a new solar panel system to generate electricity. The system will require an initial investment of ₦10 million and will generate annual savings of ₦1.5 million for the next 10 years. Calculate the payback period of the investment, assuming a discount rate of 8%.

Answer Options

A. 5 years
Correct Answer B. 6 years
C. 7 years
D. 8 years
Correct Answer
B
Correct Option:
6 years

About This Question

This is Post Utme Unilorin 2017 Geography Question 39. It is one of the objective questions from the 2017 Post Utme Unilorin Geography examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support