Post Utme Uniben 2019 Commerce Question 37
Practice objective / multiple choice question 37 from the 2019 Post Utme Uniben Commerce examination.
A firm is considering two investment projects, A and B. Project A has a 10% chance of a 20% return, and a 90% chance of a 5% return. Project B has a 20% chance of a 30% return, and an 80% chance of a 2% return. Which project has a higher expected return?