Post Utme Ui 2019 Geography Question 5

Practice objective / multiple choice question 5 from the 2019 Post Utme Ui Geography examination.

Post Utme Ui 2019 Geography Objective / Multiple Choice
Question 5 POST_UTME_UI • 2019 • GEOGRAPHY • objective

The Kainji Dam in Nigeria is a major source of hydroelectric power. What is the primary benefit of this dam?

Answer Options

A. Flood control
B. Irrigation
C. Fisheries development
Correct Answer D. Hydroelectric power generation
Correct Answer
D
Correct Option:
Hydroelectric power generation

About This Question

This is Post Utme Ui 2019 Geography Question 5. It is one of the objective questions from the 2019 Post Utme Ui Geography examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support