Post Utme Redeemers University 2025 Accounting Question 26

Practice objective / multiple choice question 26 from the 2025 Post Utme Redeemers University Accounting examination.

Post Utme Redeemers University 2025 Accounting Objective / Multiple Choice
Question 26 POST_UTME_REDEEMERS_UNIVERSITY • 2025 • ACCOUNTING • objective

A company uses the percentage of completion method to value its construction contracts. At the end of the current year, the company has completed 75% of a contract with a total contract value of ₦1,500,000. The company has incurred costs of ₦1,125,000 to date. Calculate the profit recognised for the year.

Answer Options

Correct Answer A. ₦562,500
B. ₦625,000
C. ₦750,000
D. ₦875,000
Correct Answer
A
Correct Option:
₦562,500

About This Question

This is Post Utme Redeemers University 2025 Accounting Question 26. It is one of the objective questions from the 2025 Post Utme Redeemers University Accounting examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support