A company uses the percentage of completion method to value its construction contracts. At the end of the current year, the company has completed 75% of the contract. The total contract value is ₦150,000,000. The company has incurred costs of ₦90,000,000. Calculate the profit recognized for the year.

Answer Options

Correct Answer A. ₦67,500,000
B. ₦45,000,000
C. ₦22,500,000
D. ₦30,000,000
Correct Answer
A
Correct Option:
₦67,500,000

About This Question

This is Post Utme Pan Atlantic University 2021 Accounting Question 28. It is one of the objective questions from the 2021 Post Utme Pan Atlantic University Accounting examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support