A company uses the percentage of completion method to value its construction contracts. At the end of the current year, the company has completed 75% of the contract. The total contract price is ₦120,000,000. The company has incurred costs of ₦90,000,000. Calculate the profit recognized for the year.

Answer Options

A. ₦60,000,000
Correct Answer B. ₦75,000,000
C. ₦90,000,000
D. ₦105,000,000
Correct Answer
B
Correct Option:
₦75,000,000

About This Question

This is Post Utme Osustech 2023 Accounting Question 31. It is one of the objective questions from the 2023 Post Utme Osustech Accounting examination.