Post Utme Oau 2024 Geography Question 30
Practice objective / multiple choice question 30 from the 2024 Post Utme Oau Geography examination.
A company is planning to build a new factory in a region with a high concentration of limestone deposits. The factory will require 100,000 tons of limestone per year. If the company can extract 50 tons of limestone per hour, how many hours will it take to meet the factory's annual demand?