Post Utme Oau 2024 Accounting Question 1

Practice objective / multiple choice question 1 from the 2024 Post Utme Oau Accounting examination.

Post Utme Oau 2024 Accounting Objective / Multiple Choice
Question 1 POST_UTME_OAU • 2024 • ACCOUNTING • objective

A company uses the percentage of completion method to account for construction contracts. At the end of the year, the company has incurred costs of ₦1,500,000 and earned revenue of ₦1,800,000. The contract is 75% complete. Calculate the profit or loss for the year.

Answer Options

A. ₦150,000
Correct Answer B. ₦200,000
C. ₦250,000
D. ₦300,000
Correct Answer
B
Correct Option:
₦200,000

About This Question

This is Post Utme Oau 2024 Accounting Question 1. It is one of the objective questions from the 2024 Post Utme Oau Accounting examination.