Post Utme Mountain Top University 2021 Geography Question 4

Practice objective / multiple choice question 4 from the 2021 Post Utme Mountain Top University Geography examination.

Post Utme Mountain Top University 2021 Geography Objective / Multiple Choice
Question 4 POST_UTME_MOUNTAIN_TOP_UNIVERSITY • 2021 • GEOGRAPHY • objective

A firm is considering two different locations for a new factory. Location A has a labor cost of ₦100 per hour and a transportation cost of ₦50 per hour, while Location B has a labor cost of ₦120 per hour and a transportation cost of ₦30 per hour. If the firm operates for 8 hours a day, what is the total cost of operating the factory at Location A?

Answer Options

Correct Answer A. ₦800
B. ₦900
C. ₦1000
D. ₦1100
Correct Answer
A
Correct Option:
₦800

About This Question

This is Post Utme Mountain Top University 2021 Geography Question 4. It is one of the objective questions from the 2021 Post Utme Mountain Top University Geography examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support