A company produces two products, X and Y, using two machines, A and B. The production process for product X requires 2 hours on machine A and 3 hours on machine B. The production process for product Y requires 3 hours on machine A and 2 hours on machine B. If the company has 12 hours of machine A time and 15 hours of machine B time available, how many units of product X and product Y can be produced?

Answer Options

Correct Answer A. 10 units of X and 15 units of Y
B. 15 units of X and 10 units of Y
C. 20 units of X and 5 units of Y
D. 5 units of X and 20 units of Y
Correct Answer
A
Correct Option:
10 units of X and 15 units of Y

About This Question

This is Post Utme Madonna University 2025 Commerce Question 14. It is one of the objective questions from the 2025 Post Utme Madonna University Commerce examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support