A company uses the percentage of completion method to value its construction contracts. At the end of the current year, the company has completed 75% of a contract that was awarded at the beginning of the year. The contract price is ₦1,500,000, and the company has incurred costs of ₦1,125,000. Calculate the profit recognized for the year.