Post Utme Lasu 2022 Geography Question 19

Practice objective / multiple choice question 19 from the 2022 Post Utme Lasu Geography examination.

Post Utme Lasu 2022 Geography Objective / Multiple Choice
Question 19 POST_UTME_LASU • 2022 • GEOGRAPHY • objective

A company is planning to establish a new factory in a region with a high level of environmental degradation. What type of environmental impact assessment should the company conduct?

Answer Options

Correct Answer A. Environmental Impact Statement
B. Environmental Risk Assessment
C. Environmental Audit
D. Environmental Management Plan
Correct Answer
A
Correct Option:
Environmental Impact Statement

About This Question

This is Post Utme Lasu 2022 Geography Question 19. It is one of the objective questions from the 2022 Post Utme Lasu Geography examination.