A company uses the percentage of completion method to account for construction contracts. If the contract price is ₦1,000,000, and the costs incurred to date are ₦600,000, what is the amount of revenue recognized if the percentage of completion is 75%?

Answer Options

Correct Answer A. ₦750,000
B. ₦600,000
C. ₦450,000
D. ₦300,000
Correct Answer
A
Correct Option:
₦750,000