Post Utme Ksu 2023 Accounting Question 12

Practice objective / multiple choice question 12 from the 2023 Post Utme Ksu Accounting examination.

Post Utme Ksu 2023 Accounting Objective / Multiple Choice
Question 12 POST_UTME_KSU • 2023 • ACCOUNTING • objective

A manufacturing company uses a job-order costing system. The company has two departments: Cutting and Assembly. The Cutting department has a balance of 10,000 in Work-in-Process Inventory and 5,000 in Finished Goods Inventory. The Assembly department has a balance of 8,000 in Work-in-Process Inventory and 3,000 in Finished Goods Inventory. What is the total amount of Work-in-Process Inventory?

Answer Options

A. ₦18,000
B. ₦20,000
Correct Answer C. ₦22,000
D. ₦24,000
Correct Answer
C
Correct Option:
₦22,000

About This Question

This is Post Utme Ksu 2023 Accounting Question 12. It is one of the objective questions from the 2023 Post Utme Ksu Accounting examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support