A company has a production process that involves two stages: cutting and sewing. The cutting stage takes 2 hours, and the sewing stage takes 3 hours. If the company wants to produce 1000 units, how many hours will it take to complete the production process?

Answer Options

A. 5 hours
Correct Answer B. 6 hours
C. 7 hours
D. 8 hours
Correct Answer
B
Correct Option:
6 hours

About This Question

This is Post Utme Ims U 2017 Commerce Question 19. It is one of the objective questions from the 2017 Post Utme Ims U Commerce examination.