A company has a production process that involves three stages: cutting, sewing, and packaging. The cutting stage takes 2 hours, the sewing stage takes 3 hours, and the packaging stage takes 1 hour. If the company wants to produce 1000 units, how many hours will it take to complete the production process?

Answer Options

A. 6 hours
B. 8 hours
Correct Answer C. 10 hours
D. 12 hours
Correct Answer
C
Correct Option:
10 hours

About This Question

This is Post Utme Ims U 2017 Commerce Question 13. It is one of the objective questions from the 2017 Post Utme Ims U Commerce examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support