A firm is considering two different production processes to produce a homogeneous product. Process A has a fixed \cost of ₦100,000 and a variable \cost of ₦50 per unit. Process B has a fixed \cost of ₦150,000 and a variable \cost of ₦30 per unit. If the market price of the product is ₦75 per unit, which production process should the firm choose?

Answer Options

Correct Answer A. Process A
B. Process B
C. Both processes are equally profitable
D. Neither process is profitable
Correct Answer
A
Correct Option:
Process A

About This Question

This is Post Utme Greenfield University 2017 Economics Question 19. It is one of the objective questions from the 2017 Post Utme Greenfield University Economics examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support