In a just-in-time (JIT) inventory system, a company orders 100 units of a product from a supplier every time the stock level falls to 50 units. If the supplier takes 5 days to deliver the order, and the company uses 20 units of the product per day, what is the maximum number of days the company can delay ordering the next batch of products without running out of stock?